In order to improve public safety and ensure the continued use of the pier, construction upgrades to repair and replace damaged piles and cross-braces will take place from March 18 - May 17, 2013 with intermittent pier closures. Below please find the construction timeline for April 2013.
April 8 - 14:
- Full time closures during the week with a potential for partial opening after work hours
- Partial openings during the weekend
April 15 - 21:
- Full time closures during the week with a potential for partial opening after work hours
- Partial openings during the weekend
April 22 - 28:
- Full time closures during the week with a potential for partial opening after work hours
- Partial openings during the weekend
April 29 - May 5:
- Full time closures during the week with a potential for partial opening after work hours
- No weekend closures
We recognize the inconvenience associated with the pier upgrade and greatly appreciate your patience during this time.